Integration of Supply Chain Planning with Time and Resource Constrained Project Scheduling Problems for Building’s Thermal Renovation Projects - Risks and Resilience of Collaborative Networks Access content directly
Conference Papers Year : 2015

Integration of Supply Chain Planning with Time and Resource Constrained Project Scheduling Problems for Building’s Thermal Renovation Projects

Shadan Gholizadeh Tayyar
  • Function : Author
  • PersonId : 967418
Jacques Lamothe
Lionel Dupont
  • Function : Author
  • PersonId : 967420

Abstract

CRIBA is a project that aims at industrializing thermal renovation processes of buildings. It consists in designing and configuring make-to-order insulated panels that will be installed on the external facade of the buildings to meet the thermal renovation objectives. Our study provides an optimization model that comprehensively plans supply chain network, which delivers insulated panels to the building’s worksites, and schedules renovation activity that should be executed at the worksites under the limited quantity of the resources’ availability. In this context, integration of supply chain planning problem with resource constrained multi project scheduling problem and time constrained project scheduling is of interest in realizing the decision making tool.
Fichier principal
Vignette du fichier
370605_1_En_53_Chapter.pdf (937.32 Ko) Télécharger le fichier
Origin : Files produced by the author(s)
Loading...

Dates and versions

hal-01437922 , version 1 (17-01-2017)

Licence

Attribution

Identifiers

Cite

Shadan Gholizadeh Tayyar, Jacques Lamothe, Lionel Dupont. Integration of Supply Chain Planning with Time and Resource Constrained Project Scheduling Problems for Building’s Thermal Renovation Projects. 16th Working Conference on Virtual Enterprises (PROVE), Oct 2015, Albi, France. pp.566-577, ⟨10.1007/978-3-319-24141-8_53⟩. ⟨hal-01437922⟩
152 View
152 Download

Altmetric

Share

Gmail Facebook X LinkedIn More